Going through the below states before equipment arrives and using our planning checklist ensures a successful startup. Following these pre-planning steps shows you the roadmap to success.
%%{init: {'theme': 'base', 'themeVariables': { 'primaryColor': '#1c6b92', 'primaryTextColor': '#3a5473', 'primaryBorderColor': '#1c6b92', 'lineColor': '#6d6e71', 'secondaryColor': '#8eaec9', 'tertiaryColor': '#c64527'}}}%%
flowchart TD
A([Start Preplanning]) --> B[ Plan DFU Installation]
B --> C[ Plan Wireless Connection]
C --> D[ Plan Plumbing & Water]
D --> E[ Plan Sensor Valve Interface]
E --> F[ Plan Operational Ownership]
F --> G([Preplanning Complete])
style A fill:#1c6b92,stroke:#1c6b92,color:#ffffff
style B fill:#ffffff,stroke:#1c6b92,color:#1c6b92
style C fill:#ffffff,stroke:#1c6b92,color:#1c6b92
style D fill:#ffffff,stroke:#1c6b92,color:#1c6b92
style E fill:#ffffff,stroke:#1c6b92,color:#1c6b92
style F fill:#ffffff,stroke:#1c6b92,color:#1c6b92
style G fill:#1c6b92,stroke:#1c6b92,color:#ffffff
| Task | Planned Y/N | Comments |
|---|
| Plan and Agree on Install Location for Digital Feed Unit and Sensor Valve Interfaces | | |
| Plan Electrical Utilities | | |
| Plan Plumbing Utilities | | |
| Review Water Supply (volume, temp, quality) | | |
| Plan Sensor Installs (location within CNC) | | |
| Plan Internet Connection | | |
| Item | Ordered Y/N | Dock Date |
|---|
| Digital Feed Unit Kits | | |
| Sensor Valve Interface Kits | | |
| Bulk Coolant | | |
| PEX Tubing (in/out of system) | | |
| Plumbing Anchors/Fittings as required | | |
| Labeling for when you pull wire and tubing | | |
| Resource | Coordinated Y/N | Finished by |
|---|
| Plumbing Labor Resources | | |
| Electrical Labor Resources - 110 VAC | | |
| IT Labor Resources for internet connection | | |
| Commissioning Labor Resources (install) | | |
| Operation Labor Resources (day-to-day) | | |
| Site-specific Notes | | |